Tracks / T08 / Production / daily-production-report

Daily production report

Output against plan, OEE in three parts, downtime ranked two ways, losses in dollars.

Check your systems against the 17 skills

Who uses itPlant manager
The problemI walk into the production meeting with yesterday's numbers half-built. We spend the hour arguing about the numbers, not the problems.
What comes outOne report: data freshness first, then output, OEE, downtime, losses in dollars and today's decisions.
Day one, exports onlyYes. Runs on exports alone. Writes nothing to any system.
With a connectorNetSuite or Infor M3 for standard cost and open work orders. A CMMS connector for maintenance in progress. No MES or historian connector ships.
Who signsScheduler, each exception

The job.

  • Builds the morning production report: output against plan by line, cell and product.
  • Shows OEE with availability, performance and quality apart.
  • Ranks the downtime log two ways: by minutes and by count.
  • Prices scrap and downtime in dollars. Lists week-over-week movers and the exceptions that need a decision today.
  • For each significant exception, drafts a reschedule or changeover move and traces its consequences.
  • Reads the consolidated dataset and opens with how fresh the data is.

From the skill's own SKILL.md, daily-production-report, in Anthropic's public plugin source.

A worked example.

The report gave no OEE figure and showed two missing days as gaps, never zero.

  1. Synthetic plant, 6:15 a.m. Anthropic's README puts this report at 60 to 90 minutes of a supervisor's morning.
  2. The report opens with safety: a saw seized after two restarts. The cause is marked proposed, with a lockout reminder.
  3. Downtime ranks two ways. By minutes, one saw breakdown leads at 1,865. By count, three causes tie at 19.
  4. No OEE figure appears. Availability needs planned time and shift hours, and the plant never configured them.
  5. Quality is computed from good and scrap counts. Two weekdays have no production rows, so they show as gaps.
  6. A second shift ran past midnight. The report shows output against plan both ways and says nobody confirmed the rule.
  7. What comes out: one report, data freshness first, then output, downtime, losses in dollars and today's decisions.
  8. Where a person signs: the scheduler accepts or rejects each drafted move. The report posts and sends nothing.

Source: Lab: Morning report from last night's exports. Figures marked synthetic come from a plant we invented.

What goes in.

  • The consolidated dataset from data-consolidate
  • Standard cost and open work orders from the ERP
  • Maintenance work orders in progress
  • A floor plan, if you want OEE drawn on the floor

What comes out: a run on a synthetic plant.

Real output from our blind run. A separate agent ran the skill as shipped on exports from a plant we invented. No real plant, no real customer. Excerpt, verbatim.

Synthetic plantmorning-plant-pulse (data-consolidate, then daily-production-report) · plugin fd30cee3 · 2026-11-17
Headline figures and today's actions
| Good output vs plan | 8 of 16 EA (50.0 percent) | 8 EA, no plan row |
| Same, if the 2nd shift belongs to the day it started | 16 of 16 EA (100 percent) | 0 EA |
| OEE | unavailable | unavailable |
| Availability | not computable: planned production time and shift hours are not configured | same |
| 2 | Production day boundary: is 2nd shift dated to the day it started or ended? | 10-30 reads 50 percent or 100 percent of plan | Confirm the rule with the supervisor | suggested: plant manager | decision |
How we ran it: field note 1

The first week.

  1. We write down shift hours and planned production time, so OEE can be computed.
  2. Run the report on last week's exports, one day at a time.
  3. The plant manager checks each day against what the meeting decided that day.

What it does not do.

  • It does not post or send. It hands back text to paste.
  • It does not reschedule. The scheduler accepts or rejects each move.
  • It does not compute OEE until shift hours and planned time are set.

What Lehvel adds.

The plugin leaves this part to you. We do it.

  • We set up the export or connector from your MES or historian, so the report reads this morning, not last week.
  • We configure shift hours and planned time, so OEE can be computed.
  • We make part identity agree across the MES and the ERP, so output joins to plan.

Who signs.

Claude drafts. A named person decides.

WhoWhereWhat it protects
SchedulerEach exceptionThe reschedule move is a draft to accept or reject. The skill does not post or send. It hands back text to paste.

Three questions the Diagnostic asks.

  1. Who builds the morning report now, and how long does it take?
  2. Are shift hours and planned production time written down where software can read them?
  3. Which MES or historian holds output and downtime?

Pick the tracks that pay first.

The Diagnostic maps your systems to the 17 skills and picks the two or three tracks to run first. The fee is credited in full to the Rollout.

You'll talk with Jason Murphy, founder.He takes the first call and leads every engagement.Bring your IT lead.

  • About 40 minutes
  • Phone or video

Times in Eastern (ET).

Choose a day and time

Checking the calendar.

We use your details to coordinate this call. No payment information is needed.

Rather call or text?Call 888-846-7772Text us

Check your systems against the 17 skills

Lehvel is an independent firm. We are not an Anthropic partner, and Anthropic has not certified us. Claude is a product of Anthropic. Anthropic's post · plugin source