Root cause and CAPA
Ranked causal chains on one verified timeline, each with the test that would confirm or kill it.
Check your systems against the 17 skills
| Who uses it | Quality engineer |
|---|---|
| The problem | The customer wants an 8D by Friday. I have three spreadsheets with three different clocks and a hunch. |
| What comes out | Ranked causal chains with the evidence for and against each, a test per chain, and a draft 8D. |
| Day one, exports only | Yes. Runs on exports alone. No connector. |
| With a connector | Microsoft 365 for historian and inspection exports. NetSuite or Infor M3 for lots and receipts. No QMS or historian connector ships. |
| Who signs | Quality owner, before anything customer-facing and at customer pack; Named owner, at supplier-caused flag |
The job.
- Puts sensor history, inspection measurements, maintenance records and prior tickets on one verified timeline.
- Runs the pattern checks in code: SPC drift, clusters by lot, shift, operator, machine and tool change, and links to maintenance events.
- Proposes ranked causal chains. Each has the evidence for it, the evidence against it, and the test that would confirm or kill it.
- Drafts the 8D.
- If the leading cause points at purchased material, raises the supplier-caused flag that starts a sourcing action.
- Never correlates two sources whose clocks it could not align.
From the skill's own SKILL.md, root-cause-capa, in Anthropic's public plugin source.
A worked example.
A supplier lot ranks first, with the evidence against it listed beside the evidence for.
- Synthetic plant. CAPA-2026-009 blamed operators for over-clamping and closed with retraining. The defect came back.
- The skill puts inspection readings, work orders and purchase orders on one timeline. It checks first that the clocks agree.
- The lot's mean sat 5.0 sigma below baseline. No inspector, part or shift pattern showed.
- Ranked first: the supplier lot, confidence medium. The evidence against it sits beside the evidence for it.
- One lot number covers four extrusion profiles, so it may be a receipt batch, not a material lot.
- Cheapest test: a calibrated micrometer on retained raw extrusion. Thin stock confirms the supplier. In-spec stock points to the floor.
- What comes out: ranked causes, tests, a draft 8D. D6 and D8 stay empty until a fix lands.
- Where a person signs: a named owner approves the supplier-caused flag. The quality owner approves the customer pack.
Source: Lab: Supplier lot trace. Figures marked synthetic come from a plant we invented.
What goes in.
- The consolidated dataset
- Historian and inspection exports
- Lots and material receipts from the ERP
- Maintenance history
What comes out: a run on a synthetic plant.
Real output from our blind run. A separate agent ran the skill as shipped on exports from a plant we invented. No real plant, no real customer. Excerpt, verbatim.
### Candidate 1 (leading): thin-wall extrusion in material lot AES-26-0914 from the supplier Link A (lot is thin): For: 20 of 20 failures on the lot; lot mean 5.0 sigma-hat below baseline; 0 of 138 on other lots (inspection_results.csv). Against: no incoming inspection, mill cert or raw-stock measurement in the data; the measurements are of finished parts. Link C (parts built from it fail): For: failures on 7 of the 11 work orders tied to the lot, all inspected ones; Against: 4 of 11 tied work orders were never inspected; one reading passed (0.1175).
The first week.
- We declare time zones and shift boundaries once, so your sources line up.
- Run it on a CAPA you closed last year.
- The quality engineer checks the ranked chains against the cause the plant signed.
What it does not do.
- It does not deliver a verdict. It ranks candidates for a person to test.
- It does not call a supplier at fault without a named owner.
- It does not send anything to a customer before the redaction review.
What Lehvel adds.
The plugin leaves this part to you. We do it.
- We fix the clocks: time zones and shift boundaries declared once, so sources line up.
- We connect the historian or SPC system read-only.
- We keep the 8D format your customers require.
Who signs.
Claude drafts. A named person decides.
| Who | Where | What it protects |
|---|---|---|
| Quality owner | Before anything customer-facing | The source NCR must be approved first. The investigation can proceed as a draft. |
| Named owner | Supplier-caused flag | A supplier-caused call is a commercial claim. It needs a named owner before it acts. |
| Quality owner | Customer pack | Nothing leaves without review of the redaction diff. |
Three questions the Diagnostic asks.
- Do your sensor, inspection and maintenance records share a clock and a time zone?
- How many CAPAs closed last year came back?
- Who owns a supplier-caused call today?
Pick the tracks that pay first.
The Diagnostic maps your systems to the 17 skills and picks the two or three tracks to run first. The fee is credited in full to the Rollout.
You'll talk with Jason Murphy, founder.He takes the first call and leads every engagement.Bring your IT lead.
- About 40 minutes
- Phone or video